KEFI Minerals selects its preferred project infrastructure finance proposal

KEFI Minerals (LON:KEFI), the gold exploration and development company with projects in the Federal Democratic Republic of Ethiopia and the Kingdom of Saudi Arabia, has announced that it has selected its preferred project infrastructure finance proposal for the Company’s Tulu Kapi Gold Project, being a bank loan based proposal recently received from two leading African banks as underwriters and co-lenders.  A preliminary term sheet has been signed and is subject to credit approval.

The bank-based proposal is considered by the directors of the Project company, Tulu Kapi Gold Mines Share Company (“TKGM”), to be financially more attractive and more straightforward to execute than the long-standing alternative bond-and-lease based debt financing proposal.  In addition, the proposed bank lenders are actively working in Ethiopia, are familiar with the local market and many of our local stakeholders and thus considered more compatible with the Project consortium.  There are no charges payable for electing not to proceed with the bond-and-lease based debt financing proposal.  The underlying economics are summarised below and compared with the previous bond-and-lease based proposal.

The proposed Project and financing timetable, as previously announced, is for the first six months of development to be funded by way of equity investment at the TKGM level by the Project partners, beginning in January 2020, with full finance close and bank loan drawdown planned for mid-2020.  The amount of Project equity (US$68 million) and subordinated working capital facility requirements (US$14-24 million) remain essentially unchanged, as is the contribution towards capital expenditure.  However, material savings are expected in the cost of debt-servicing, administration and other charges, especially during the Project development and start-up period.

Using the proposed bank loan infrastructure financing at the current gold price of US$1,450/oz, KEFI estimates that the net cash flow over the life of the open pit will increase from US$314 million to US$380 million.  On this basis, TKGM could maintain the same net cash flow for shareholders as previously projected, while at the same time funding the development of the underground mine, which requires an estimated capital expenditure of US$37 million per its Preliminary Economic Assessment (“PEA”).  This is expected to significantly increase production, mine life and the overall Project NPV.

At the current gold price of US$1,450/oz, the Definitive Feasibility Study or DFS-based NPV of the open pit (US$171 million) added to that of the PEA-based NPV of the underground mine (US$74 million), totals to the aggregate Project NPV of US$245 million.  

On this basis and after taking into account that KEFI has already invested nearly all of its contribution to the Project equity, KEFI’s 45% beneficial interest is US$130 million (approximately £101 million), about eight times the current market capitalisation of the Company. 

This does not include further potential upside offered by exploration underground where extensions of the 5.6 g/t Indicated Resource remain untested, in the adjacent Tulu Kapi district, where several areas of drill-intercepted pre-resource mineralisation require follow-up and in Saudi Arabia where drilling is currently intercepting massive sulphides in a large Volcanogenic Massive Sulphide occurrence.

KEFI Finance Director, Mr John Leach, commented, “We have been very well supported by the bond-lease proposal and now we also have an attractive bank-loan based alternative because capital market support for our Project has recently improved markedly, both inside and outside Ethiopia.  The expected savings from the preferred bank-based infrastructure finance proposal provide our Project subsidiary, TKGM, with the opportunity to develop and further explore the underground Tulu Kapi deposit and significantly increase value for shareholders, without reducing net cash flows available for other purposes.”

Comparison of selected bank-loan-based proposal compared with previous bond-lease-based proposal

Excluding the past investment of c. US$55-US$60 million to the end of 2018 and also excluding the c. US$50 million mining equipment to be supplied by the mining contractor, the overall funding plan for Tulu Kapi is summarised below which compares the bank-loan and the bond-lease approaches. Both proposals remain subject to due diligence and full legal documentation and, as part of those processes, all key independent expert reports will be updated nearer to full financial closing:

Funding RequirementsBank-LoanUS$mBond-LeaseUS$m
On-site Infrastructure106.3106.3
Mining28.628.6
Off-site Infrastructure20.020.0
Owner’s Costs (community, working capital, finance administration, costs & reserves to protect financiers)33.554.5
Interest during grace and other finance effects17.332.8
Aggregate Funding Requirements205.7242.2
Sources of FundsBank-LoanUS$mBond-LeaseUS$m
TKGM Project Equity

  – Government20.020.0
  – ANS Mining38.038.0
  –  KEFI10.010.0
Subordinated Working Capital Facility17.7 – 27.714.2 – 24.2
Sub-Total   85.7 – 95.782.4 – 92.4
Infrastructure Finance110.0-120.0150.0-160.0
Aggregate of Funding Sources205.7242.2
 

Comparative Economics:

Net Cash Flow over life of Open Pit Mine379.5313.6
Average Debt Service Coverage Ratio2.8X1.8X
Loan (prepayment possible) or Bond Tenor7.5 years9.0 years
Average Cost per Year Over Life of Loan8.711.6

Note: The KEFI equity contribution sourced from cash, working capital facility and refunds on closing of full funding.

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
Twitter
LinkedIn
KEFI Minerals Plc

More articles like this

KEFI Gold and Copper

KEFI Gold and Copper at Africa Down Under 2023

London-listed company KEFI Gold and Copper plc (LON:KEFI) is an exploration and development company focused on gold and copper deposits in the highly prospective Arabian-Nubian Shield. The Company operates in Ethiopia and Saudi Arabia with projects including Tulu

KEFI Gold and Copper

Recent developments put KEFI’s Tulu Kapi into the spotlight

Three recent developments have served to put KEFI’s Tulu Kapi into the spotlight. The first is Ethiopia’s recent central bank directive exempting certain strategic industries – including mining – from foreign exchange controls, satisfying the last

KEFI Gold and Copper

East Africa and Ethiopia attracting investment

Three recent developments have served to put KEFI’s Tulu Kapi into the spotlight. The first is Ethiopia’s recent central bank directive exempting certain strategic industries – including mining – from foreign exchange controls, satisfying the last

KEFI Gold and Copper

KEFI nearly ready to start construction at Tulu Kapi

Gold and copper exploration and development company Kefi Gold and Copper has announced that almost all the prerequisites to begin construction at the Tulu Kapi gold project, in Ethiopia, are now in place. The company revealed details of where the project stands in an operational update issued on September 5

KEFI Gold and Copper

Gold prices inch higher

Gold prices inched higher on Thursday, as a slight pullback in Treasury yields offered some respite from a robust dollar, while investors looked forward to more U.S. economic data to gauge the outlook for interest rates.

KEFI Gold and Copper

KEFI Gold and Copper updates on operations in Saudi Arabia

KEFI Gold and Copper Plc (LON:KEFI), the gold and copper exploration and development company which has focused on the Arabian-Nubian Shield since 2008, has provided an operational update covering recent developments in Saudi Arabia and the Company’s minority-owned Gold

KEFI Gold and Copper

Gold price rises to near month high

Gold rose for a third straight session on Wednesday, supported by a fresh batch of weak US economic data which reinforced the view that the Federal Reserve may have to hit pause on its interest rate

KEFI Gold and Copper

Gold climbs to two-week peak

Gold rose for a fourth straight session to a two-week high on Thursday, extending gains from the previous session fuelled by weaker U.S. data in the run up to likely interest rate guidance from central bankers

KEFI Gold and Copper

Copper rebounds on softer dollar

Copper prices rose on Tuesday from a six-week low hit in the previous session, on expectations of improvingdemand as top metals consumer China cut policy rates, and as a softer dollar made greenback-priced metals cheaper to holders of other currencies. Three-month copper

KEFI Gold and Copper

KEFI Gold and Copper ready for mine construction

KEFI Gold and Copper is gearing up to begin the first phase of its Tulu Kapi gold mine project after securing funding for development in June. According to the company, Tulu Kapi Gold Mines plans to

KEFI Gold and Copper

KEFI Gold and Copper progress on all fronts

KEFI Gold and Copper (LON:KEFI), the gold and copper exploration and development company, has focused on the Arabian-Nubian Shield since 2008, assembling a pipeline of projects in the Kingdom of Saudi Arabia and in the Federal Democratic

KEFI Gold and Copper

Tulu Kapi Gold Mine to begin operations in September

The Tulu Kapi gold mine, which is Ethiopia’s first modern industrial-scale gold producer, is scheduled to begin operations in September. The mine has a capital investment of over 500 million USD and has completed all necessary

KEFI Gold and Copper

Gold prices tick up as traders await Fed cues

Gold prices edged up on Tuesday on a dollar that was close to hitting its lowest in over a year, while traders waited for retail sales data from the United States to gauge any impact on

KEFI Gold and Copper

Gold rises on softer dollar

Gold prices rose on Wednesday after the dollar and bond yields retreated as investors awaited U.S. inflation data that could offer more cues on the Federal Reserve’s rate-hike policy path. Spot gold rose 0.4% to $1,939.43 per ounce by