KEFI Gold and Copper’s Tulu Kapi Gold Project remains on track

KEFI Gold & Copper plc (LON:KEFI), the gold and copper exploration and development company with projects in the Federal Democratic Republic of Ethiopia and the Kingdom of Saudi Arabia, has provided an operational update.

Ethiopia

Today is election day in Ethiopia. These are widely regarded as the most important elections in the country’s history. The electioneering atmosphere in the lead-up around the country has been one of vibrant, but peaceful campaigning, reflecting very positively on the reforms over recent years. Ethiopia remains amongst the highest growth countries in Africa and the world, whilst it continues to push its agenda of liberal and democratic reform.

Tulu Kapi Project Finance

The Tulu Kapi Gold Project remains on track with previous guidance and KEFI, through its subsidiary Tulu Kapi Gold Mines Share Company, has presented its Project finance syndicate and submitted its Project finance plan to the Ethiopian central bank for permission that it may proceed as outlined. This follows a long, thorough and rigorous due diligence process by the Senior Lenders.

Whilst the NBE conducts its review, the other outstanding administrative details are being progressed with the various Ethiopian Government agencies including, the Ministry of Mines and Petroleum (“MOMP”), Ministry of Finance, Ethiopian Roads Authority and Ethiopian Electricity Power Corporation. These are normal compliance procedures to enable KEFI/TKGM and its syndicate of financiers and contractors to proceed to financial closing, which includes, inter alia, execution of detailed documentation, subscription of the asset-level equity funds and triggering full development, with debt funds to be disbursed later this year in compliance with the Senior Lenders specified conditions.

These procedural matters include requests for finalising confirmations of registration of historic investment, establishment of correspondent bank account arrangements, confirmation of construction schedules for road and electricity, and various other administrative matters already agreed in principle.

Starting full development of the Project is the highest priority for KEFI and the Ethiopian Government. All key stakeholders are pushing hard to finalise preparations and the Company has undertaken to the MOMP that, upon timely receipt of these confirmations, KEFI will push to financial closing by the end of July 2021, or as near as possible thereto given the local document registration procedures and the COVID-affected limitations of syndicate parties’ physical locations.

Recent Tulu Kapi Project Activities

KEFI continues to oversee the physical preparations for full development to be triggered at financial closing, such as:

• Clearing of new host lands for community members to be resettled;

• Overseeing the early works programme of detailed engineering and procurement, by principal construction contractor Lycopodium;

• Supporting the planning and procurement programmes of mining services contractor Corica;

• Overseeing the ‘new access road’ and ‘electricity connection’ works contracts; under which surveys and procurement has been completed;

• Triggering compensation procedures for the first resettlers at the Tulu Kapi electrical substation site; and

• Recruitment of further key personnel for the next stage of the Project.

Saudi Arabia

Hawiah Gold Project

KEFI’s operations in Saudi Arabia are conducted through its 34% owned joint-venture company, Gold & Minerals Ltd (“G&M”), where KEFI is the operating partner.

G&M are working to finish the Phase 4 drilling programme in Q3 2021 with the goal of reporting an expanded and upgraded Mineral Resource. With Ramadan having ended, drilling since late May 2021 has been 24/7 with three rigs on site.

The Preliminary Feasibility Study for the potential start of development of the Hawiah deposit in 2023 continues, and other recent activities have included the following:

• Completion of the Environmental and Social Baseline Study;

• Metallurgical testing progressing with reasonable recoveries so far being indicated for all principal metals, copper, gold, zinc and silver; and

• Completion of the exploration camp construction.

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
Twitter
LinkedIn
KEFI Gold and Copper

More articles like this

KEFI Gold and Copper

Copper prices soar to 11-month high on Chinese smelter cuts

Copper prices soar to an 11-month high as Chinese smelters cut production, sparking potential long-term investment opportunities. Copper prices skyrocketed to over $4.1 per pound, hitting their highest point in more than eleven months. This surge

KEFI Gold and Copper

Gold prices near two-month high

Gold prices lingered close to a two-month high on Monday, after softer US economic readings last week cemented prospects of an interest rate cut in June by the Federal Reserve. Spot gold edged 0.1% lower to

KEFI Gold and Copper

KEFI unveils Abu Salal deposit in Saudi Arabia

KEFI Gold and Copper has unveiled the discovery of a third significant copper-gold deposit within the expansive Hawiah Copper-Gold district in Saudi Arabia. This follows the original Hawiah discovery when drilling commenced in 2019 and the

KEFI Gold and Copper

Tulu Kapi stakeholders commit to proceed with project development

Following meetings with senior representatives of stakeholders for aim-listed Kefi Gold and Copper’s Tulu Kapi gold project, in Ethiopia, at this year’s Investing in African Mining Indaba, all parties in the funding syndicate for the project will go to their respective committees this month to

KEFI Gold and Copper

KEFI discovers new high-grade Gold Deposit in Saudi Arabia

Aim-listed Kefi Gold and Copper has confirmed a new discovery, as well as provided an operational update for the Jibal Qutman gold project in Saudi Arabia in the company’s minority-owned Gold and Minerals (GMCO) joint venture (JV). A satellite deposit, Asfingia, was discovered with “excellent”