Edenville Energy plc update to shareholders and overview for Q1 work programme.

Edenville Energy plc (AIM: EDL) the company developing a coal to power project in south western Tanzania, has today updated shareholders and provides an overview of the work programme for Q1, 2016.  This builds upon the considerable progress made during 2015.

 

 

Quarter 1 2016 Work Plan – Collaboration Agreement, Project Development

 

Following on from our recent Collaboration Agreement, Edenville and Runh Power have agreed on a work programme for Q1 2016.  The initial phase of the work programme comprises of multiple meetings with Tanzanian Government Organisations and technical analysis at the Rukwa site, to progress the Rukwa Coal to Power Project in accordance with Tanzania’s Power Development Plan. 

 

Edenville and Runh Power will work closely to action the remaining bankable feasibility work, expanding the Lahmeyer Rukwa Power Plant Feasibility Study (2015) to generate a definitive technical study and financial model which will underpin Power Purchase Agreement (‘PPA’) negotiations with the Tanzanian Government and advance financing options with suitable institutions.

 

Mining Licence Update

 

The mining licence application process is ongoing. The application has reached the stage of being placed on the MEM Cadastre system with the status of “Application Recommended”.  It is now awaiting the input of senior officials in the Ministry of Energy and Minerals (MEM) to complete the process.

 

Geophysics

 

The geophysical survey (ground magnetics) initiated in early 2015 aims to better delineate the boundaries of the coal basins and possible extensions outside the existing resource has been completed over the Namwele – Mkomolo region. A total of 116 survey lines at a spacing of 250m over the entire 16kms of Karoo basin was completed. This work totalled over 400 line km of survey work.

 

This data base will be forwarded to a geophysical consultant for final analysis and interpretation during 2016.

 

Outlook

 

The Company sees 2016 as a transformational year for the Rukwa Coal to Power Project, and continues to focus on securing a Power Purchase Agreement and project level finance prior to commencement of construction.  

Click to view all articles for the EPIC:
Or click to view the full company profile:
    Facebook
    X
    LinkedIn
    Edenville Energy Plc

    More articles like this

    Edenville Energy Plc

    Edenville Energy much improved performance at Rukwa

    Edenville Energy Plc (LON:EDL) has provided a production update regarding its Rukwa Coal Project. A total of 594 tonnes of coal were washed at Rukwa in March 2023. Of this, 512.5 tonnes of coal were washed from

    Eden Research

    Edenville Energy updates on Rukwa Coal Project

    Edenville Energy Plc (LON:EDL) has provided an update on operations at its Rukwa Coal Project in Tanzania. Following the recommencement of production at Rukwa, as announced on 11 October 2022, the Company is pleased to report

    Edenville Energy Plc

    Edenville Energy production recommenced at Rukwa Coal Project

    Edenville Energy Plc (LON:EDL) has provided an update on operations at its Rukwa Coal Project in Tanzania. Highlights –      Production recommenced at Rukwa at an initial 4,000 tonnes per month of washed coal –      Completed overhaul of wash plant

    Edenville Energy Plc

    Edenville Energy to expand operations at Rukwa

    Edenville Energy plc (LON:EDL) has announced that, following a period of previously announced disappointing performance at Rukwa Coal Project, a new experienced on-site management team has been mobilised to run its mine at Rukwa in Western

    Edenville Energy Plc

    Edenville Energy signs new coal mining contract with Nextgen

    Edenville Energy Plc (LON:EDL) has announced its subsidiary Edenville International (Tanzania) Limited has entered into a contract with Nextgen Coalmine Limited for the operation of the Company’s Rukwa Coal Project in Tanzania..  The Agreement is for

    Edenville Energy Plc

    Edenville Energy appoint Tavira Securities as broker

    Edenville Energy Plc (LON:EDL) has announced the appointment of Tavira Securities Limited as broker to the Company. Tavira has recruited senior personnel that managed the Edenville relationship for the Company’s former broker, Brandon Hill Capital Limited, including Oliver Stansfield