Pensana plc pleased with progress at Saltend and Longonjo

Following the Company’s operational update of 26 October 2022, Pensana Plc (LON:PRE) has now reported that Project Delivery Teams for each of the Saltend and Longonjo projects have moved on-site and have commenced the early construction programmes.

Saltend

At Saltend, the Company’s principal contractor, Wood, is on-site, overseeing Yorkshire Water’s nominated contractor for the relocation of existing pipework along the site’s western boundary. This is progressing well as part of the activities to enable the main contractual works to commence early in the New Year.

The contracts for the earthworks have been assessed for imminent award, per the construction plan schedule, and are overseen by the Wood, which has been appointed to supervise these contracts alongside Pensana’s recently appointed owners’ team construction manager, Mark O’Rourke. 

Saltend now has 24/7 site security following the installation of the construction offices, security and welfare cabins and the development of the site access locations.  

Longonjo

The Longonjo earthworks and civils contractor, Grupo Nov, has mobilised to site. Ground clearing of the area for the main construction camp has been undertaken. The fabrication of the construction camp buildings by Bushtec at their plant in South Africa, is progressing well and is on schedule for delivery to site in January 2023.

Kick-off site sessions were held with the sub-contractors appointed for site electrical reticulation (Electra) and main HT/LT sub-stations (Enerline), who completed their pre-mobilisation site inspections alongside the Pensana owners’ team.

Contractors associated with the process water supply (ERM), tailings storage facilities (SRK), and waste management services (AES) have participated as part of the ongoing detailed design development workstreams.

Under the Stakeholder Engagement Program, updates on the Longonjo site activities were presented by Project Director, Kevin Botha, to the Governor of Huambo and the Longonjo Administrator.

Sessions have been held with Port of Lobito operations and local suppliers of construction materials to confirm arrangements for the main construction requirements.

Environment Social Governance (ESG)

Pensana’s ESG commitment to ensure direct long-term economic benefit to Longonjo’s local communities is progressing well. Demonstration farming plots have been installed on a dedicated area with multiple purposes of livelihood restoration. This has demonstrated increased yields and crop optimisation, providing food security for the Longonjo operations and delivering economic benefit to the region. The demonstration plots also allow Pensana to assess the most successful strategies to increase and enhance the natural habitat, leading to an overall biodiversity net gain.

Operational readiness

Recruitment of key operational personnel for both Saltend and Longonjo is continuing. The intention is for key operators to be part of the construction process to assist them moving seamlessly into commissioning.

Tim George Pensana plc CEO commented:

“Following our previous update in October we are extremely pleased with the progress at both sites. Our early construction management team has continued to grow with the addition of Mark O’Rourke appointed as a construction manager in Saltend. 

The enabling works appointed last month are on-site delivering to project schedule and making good progress. These critical developments will allow us to move forward quickly in delivering independent and sustainable world-class rare earth facilities at both our operations.” 

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
X
LinkedIn
Pensana plc

More articles like this

Pensana plc

US grant boosts Angola’s critical mineral sector

A recent statement from the White House has brought attention to the US$ 3.4 million technical assistance grant provided to Pensana in October. This grant is aimed at expanding the company’s mining operations, with a focus

Pensana plc

Advancing global climate and energy solutions

The U.S. International Development Finance Corporation (DFC) has announced over $3.7 billion in climate finance investments for Fiscal Year 2024, marking a significant stride in addressing global climate and energy challenges. This commitment underscores the U.S.

Pensana plc

Leading sustainable rare earth supply in Europe

Leading sustainable rare earth supply in Europe The rare earth elements (REE) sector has emerged as one of the most strategically important industries in today’s global economy. As critical inputs for modern technology, these elements play

Pensana plc

Industrial uses and global production of Rare Earth Elements

Rare earth elements, a group of 17 metallic elements, possess unique magnetic, luminescent, and electrical properties that make them valuable for various industrial uses. Despite the presence of these elements in mineral ores worldwide, their production

Pensana plc

Rare Earth Elements in high-tech and energy devices

Rare-earth elements (REEs) play a critical role in a range of high-tech devices, from smartphones and digital cameras to computer hard disks and electronic displays. They are also vital to clean energy initiatives and defence technologies,

Pensana plc

The unique qualities and future potential of Rare-Earth Elements

The unique properties of rare-earth elements (REEs) make them critical to many high-tech applications. Despite the misleading name, these elements are not particularly scarce in the Earth’s crust, though they are typically found in low concentrations.