Pensana plc (LON:PRE) has provided the following update on the Longonjo project:
Concrete foundations have been poured for the 316-person modular camp manufactured in South Africa for despatch to site later this month.
The on-site team, under the leadership of experienced Project Manager Kevin Botha, is continuing to make good progress with preparatory works ahead of main construction anticipated in May 2024, with cold commissioning commencing in August 2025.
An order has been placed with NCP International, a global supplier of new and refurbished comminution equipment based in South Africa, for the US$2.3 million ball mill for delivery from Johannesburg to meet the construction and commissioning timelines for the concentrator plant.