First gas from Touchstone expected in May

There is more encouraging news in the energy sector as Paul Baay the President and Chief Executive officer of Touchstone Exploration company has revealed that the first gas from its Coho discovery to flow in early May with production from its Ortoire discoveries by the end of the year.

This according to Baay will lead to an addition of 100 million standard cubic feet of natural gas to the national production, all of which will go into petrochemicals and electricity.

In an interview with the Business Guardian Baay said, “The first gas that we are looking at Ortoire would be early May and then the second phase that we are looking at, which is the second facility coming on stream would come on in ahh, we are hoping for the start of August time frame.

The first phase is about 10 million standard cubic feet per day (mmscf/d) and the second phase 60 mmscf/d, getting ramped up to 90 mmscf/d during 4th quarter, so by the end of the year about 100 mmscf/d will be coming out of Ortoire.”

Click to view all articles for the EPIC:
Or click to view the full company profile:
Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn

More articles like this

Can Trinidad & Tobago help fill Europe’s gas shortfall?

With Europe pushing hard to reduce their reliance on Russian gas, in the aftermath of the invasion of Ukraine, Trinidad & Tobago’s Liquified Natural Gas (LNG) exports have come into the geopolitical spotlight, and this has also brought

Touchstone’s Trinidad project gets go ahead

Toronto-listed independent Touchstone Exploration on August 17 it had received a certificate of environmental clearance to move ahead with development of its Cascadura gas project in Trinidad and Tobago’s onshore Ortoire block. The sanction from Trinidad’s Environmental Management

Young optimistic over new Touchstone wells

Energy Minister Stuart Young has expressed optimism over two new wells being drilled onshore in the Ortoire Licence area by an independent Canadian company, Touchstone Exploration. These are the Coho and Cascadura wells. In a tweet on Wednesday,

Touchstone Exploration sales lifted by higher oil prices

Touchstone Exploration Inc – Calgary, Canada-based upstream oil and gas company – Achieves quarterly average crude oil production volumes of 1,420 barrels per day, up 2% on a quarter before and up 1% year-on-year. Achieves petroleum sales of

Touchstone Exploration excited to ramp up production (VIDEO)

Touchstone Exploration (LON:TXP) CEO Paul Baay joins DirectorsTalk Interviews to discuss the Environmental Impact Assessment. Now that the Environmental Management Authority have confirmed that the Environmental Impact Assessment is complete Paul explains what this means for the Cascadura well,

Touchstone Exploration CEC application in process

Touchstone Exploration Inc (LON:TXP) has announced that the Trinidad and Tobago Environmental Management Authority has confirmed that no further information is required regarding the Cascadura Environmental Impact Assessment. The Cascadura EIA supports the Company’s application for a Certificate of

Touchstone prepares for Coho launch in Trinidad

Touchstone Exploration has filed a notice to local residents that it will start pre-commissioning and commissioning operations at the Coho gas facility at the Ortoire block in Trinidad and Tobago, the London-listed company announced on August 3. Coho is one

Touchstone Exploration progressing towards full commercial production

Touchstone Exploration Inc (LON:TXP) has announced that the Company has summitted a notice to residents in the community that the Coho gas facility and pipeline will commence pre-commissioning and commissioning operations. Pursuant to the Coho Certification of Environmental

Touchstone to meet with EMA

Touchstone Exploration has provided an additional update on the status of an Environmental Impact Assessment for the Cascadura area of its Ortoire block. In a statement, the company noted that the EIA, which is in support of an

Touchstone projects high gas yield from Cascadura field

By 2023, the Touchstone Exploration (Trinidad) Ltd Cascadura Field project is expected to produce up to 200 million standard cubic feet per day (mmscf/d) of natural gas with the aid of its new separators. On Friday, the company