Pensana site preparation works well underway at Longonjo

Pensana plc (LON:PRE) has provided the following update on the Longonjo project:

Concrete foundations have been poured for the 316-person modular camp manufactured in South Africa for despatch to site later this month.

The on-site team, under the leadership of experienced Project Manager Kevin Botha, is continuing to make good progress with preparatory works ahead of main construction anticipated in May 2024, with cold commissioning commencing in August 2025.

An order has been placed with NCP International, a global supplier of new and refurbished comminution equipment based in South Africa, for the US$2.3 million ball mill for delivery from Johannesburg to meet the construction and commissioning timelines for the concentrator plant.

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
Twitter
LinkedIn
Pensana plc

More articles like this

Pensana plc

Unlocking Angola’s untapped mineral wealth

Angola, the seventh-largest country in Africa, is most well-known for being one of the region’s biggest oil exporters. The commodity provides around half of the country’s fiscal revenues, yet it is not oil that is piquing renewed

Pensana plc

Pensana reports enriched rare earths findings in Angola

UK-based rare earths developer Pensana has reported trench and pit sampling results that confirm a 6 ha, enriched laterite at Sulima West, in Angola, grading at 2% to 3% total rare earth oxides (TREO). These analytical

Pensana plc

Pensana advances preparatory works for Longonjo project in Angola

Preparatory works are forging ahead smoothly at rare earths mining company Pensana’s Longonjo project in Angola, with main construction expected to start in May and cold commissioning to follow in August 2025. Longonjo is one of the world’s largest undeveloped rare earth