Touchstone Exploration progressing towards full commercial production

Touchstone Exploration Inc (LON:TXP) has announced that the Company has summitted a notice to residents in the community that the Coho gas facility and pipeline will commence pre-commissioning and commissioning operations. Pursuant to the Coho Certification of Environmental Clearance, residential notification is required to be made a minimum of five business days prior to the commencement of operations. The Coho area is located in the Ortoire block, where Touchstone has an 80 percent operating working interest and Heritage Petroleum Company Limited holds the remaining 20 percent working interest.

The pre-commissioning of the gas facility and pipeline consists of testing all electronics, alarms, and operating systems in the facility, testing of the flare and emergency shutdown systems, as well as purging air from the system using inert nitrogen gas. Subsequent to these operations, system commissioning operations will commence, which entails the introduction of natural gas from the Coho-1 well into the facility and pipeline in a step rate manner, officially bringing the system onstream to the Central block natural gas facility.

Coho-1 will commence production following completion of the commissioning and pipeline handover process, with the expectation that production will increase over time to 10 MMcf/d (1,667 boe/d) gross, 8 MMcf/d (1,333 boe/d) net. Touchstone will provide further information once production is optimized through the system.

Paul Baay, Touchstone Exploration President and Chief Executive Officer, commented:

“The completion of the Coho facility and pipeline will be a significant milestone for Touchstone, as it will represent our first natural gas production and is expected to double our current production on a boe basis. Throughout this process we have encountered challenges that have provided us valuable knowledge to streamline the construction of the Cascadura facility. During the pre-commissioning and commissioning process, we will need to balance the system with the well, pipeline and Central block facility. We will keep all stakeholders informed of our progress, and I would personally like to thank our shareholders for their continued patience as we proceed to full commercial production.”

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
Twitter
LinkedIn
Touchstone Exploration

More articles like this

Touchstone Exploration

Touchstone acquires Trinity Exploration in $30.1m all-stock deal

Touchstone Exploration has agreed to acquire Trinity Exploration and Production, a crude oil exploration, development and production company operating in Trinidad and Tobago, in an all-stock deal worth around $30.1m. Trinity Exploration and Production holds producing

Touchstone Exploration

Touchstone Exploration increases funding facility

Touchstone Exploration Inc (LON:TXP) has announced that, further to the announcement on March 4, 2024, Touchstone Exploration (Trinidad) Ltd., our wholly owned Trinidadian subsidiary, has entered into the third amended and restated loan agreement with our Trinidad

Touchstone Exploration

Touchstone adds wells into Ortoire and CO-1 blocks

Touchstone Exploration Inc. has drilled wells into Ortoire and CO-1 blocks onshore Trinidad and Tobago and expects to test wells in Cascadura field later in the year. Cascadura-3ST1 delineation well was spudded on Mar. 4, 2024,

Touchstone Exploration

Natural Gas price surges on supply decline forecast

Natural Gas (XNG/USD) price soars higher on Tuesday after a stellar performance on Monday, trading up nearly 3% for the week. The move comes as Bloomberg forecasts a decline in Gas supply by 4% in the coming weeks

Touchstone Exploration

Natural Gas futures gain on cold weather forecast

Natural gas futures pulled back from early highs, still ending the week’s opening session with a gain as near-term cold weather that could prevent surpluses in natural gas inventories from widening further offered some support. U.S.