Touchstone Exploration progressing towards full commercial production

Touchstone Exploration Inc (LON:TXP) has announced that the Company has summitted a notice to residents in the community that the Coho gas facility and pipeline will commence pre-commissioning and commissioning operations. Pursuant to the Coho Certification of Environmental Clearance, residential notification is required to be made a minimum of five business days prior to the commencement of operations. The Coho area is located in the Ortoire block, where Touchstone has an 80 percent operating working interest and Heritage Petroleum Company Limited holds the remaining 20 percent working interest.

The pre-commissioning of the gas facility and pipeline consists of testing all electronics, alarms, and operating systems in the facility, testing of the flare and emergency shutdown systems, as well as purging air from the system using inert nitrogen gas. Subsequent to these operations, system commissioning operations will commence, which entails the introduction of natural gas from the Coho-1 well into the facility and pipeline in a step rate manner, officially bringing the system onstream to the Central block natural gas facility.

Coho-1 will commence production following completion of the commissioning and pipeline handover process, with the expectation that production will increase over time to 10 MMcf/d (1,667 boe/d) gross, 8 MMcf/d (1,333 boe/d) net. Touchstone will provide further information once production is optimized through the system.

Paul Baay, Touchstone Exploration President and Chief Executive Officer, commented:

“The completion of the Coho facility and pipeline will be a significant milestone for Touchstone, as it will represent our first natural gas production and is expected to double our current production on a boe basis. Throughout this process we have encountered challenges that have provided us valuable knowledge to streamline the construction of the Cascadura facility. During the pre-commissioning and commissioning process, we will need to balance the system with the well, pipeline and Central block facility. We will keep all stakeholders informed of our progress, and I would personally like to thank our shareholders for their continued patience as we proceed to full commercial production.”

Click to view all articles for the EPIC:
Or click to view the full company profile:
Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Touchstone Exploration

More articles like this

Touchstone Exploration

Oil & gas field profile: Cascadura Conventional Gas Field

Cascadura is a producing conventional gas field located onshore Trinidad and Tobago and is operated by Primera Oil and Gas. According to GlobalData, who tracks more than 34,000 active and developing oil and gas fields worldwide, the field is

Touchstone Exploration

Touchstone sees increase in T&T energy reserves

Canadian oil and gas company Touchstone Exploration Inc has released the findings of an independent year-end evaluation which shows that the company is defining new reserves in T&T faster than it can extract them. Touchstone, which is active

Touchstone Exploration

TT’s Touchstone hits stride with Cascadura project

Trinidad-based Touchstone Exploration is celebrating success with its Cascadura project, evident from the company’s third-quarter results released on November 14. The impact of Cascadura’s initial output on both production profile and operating cash flows has been substantial, as

Touchstone Exploration

Touchstone Q3 2023 financial and operating results

Touchstone Exploration provided an operational update and reports its operating and financial results for the three and nine months ended September 30, 2023. Unless otherwise stated, all financial amounts presented herein are rounded to thousands of United States dollars,

Touchstone Exploration

Natural gas price still bullish

Natural gas price lost the positive momentum recently after stochastic decline below 50 level, to force it to postpone the bullish rally and provide new sideways fluctuation by settling near 3.400. We will depend on the stability of

Touchstone Exploration

Natgas prices jump 7% to nine-month high

U.S. natural gas futures jumped about 7% to a nine-month high on Tuesday on forecasts for colder weather and higher heating demand over the next two weeks than previously expected. Futures “are seeing large gains today after sudden

Touchstone Exploration

Trinidad and Tobago’s energy industry

Trinidad and Tobago’s oil and gas industry has had operations for more than a century and now supports the largest hydrocarbons production in the Caribbean. In the 1990s, the country successfully transitioned from an oil-dominated industry towards becoming

Touchstone Exploration

Natural gas prices rise on Israel concerns

Natural gas prices have jumped this week in Europe on worries about supplies stemming from the conflicts in Israel and Ukraine. Prices for benchmark European gas contracts are up more than 20 percent since the end of last

Touchstone Exploration

Touchstone focusing on Coho & Cascadura gas supply

Toutchstone Exploration Inc’s focus going forward in Trinidad and Tobago will be to fill up the gas facilities at Coho and Cascadura as quickly as possible, its president and chief executive officer, Paul Baay, has said. Baay made

Touchstone Exploration

Trinidad hits projected gas production at onshore field

Touchstone Exploration has hit its forecasted gas production volumes at the onshore Cascadura field in Trinidad and Tobago, the Canadian independent announced on Monday. The field located on the 181-square-kilometre Ortoire block began production earlier this month and has

Touchstone Exploration

Touchstone Exploration hosting Capital Markets Day today at 9am

Touchstone Exploration Inc (LON:TXP) is hosting a Capital Markets Day event for analysts and investors today at 9 a.m. BST at the offices of FTI Consulting. At the CMD, Touchstone Exploration’s senior management team will present further details regarding the

Touchstone Exploration

Touchstone’s first oil production meets expectations

Touchstone Exploration Inc announced that it achieved its gross natural gas production target at the Cascadura field in Ortoire after the first week of operations. Touchstone has an 80 per cent operating working interest in the Cascadura field,

Touchstone Exploration

Minister Young meets with Touchstone Board

The Minister of Energy and Energy Industries and Minister in the Office of the Prime Minister, Stuart R. Young, M.P., met with the board of directors at Touchstone Exploration Inc. The meeting took place at the Hyatt Regency

No more posts to show