Touchstone Exploration Inc (LON:TXP) has provided an operational update, highlighted by drilling results at our Cascadura-3ST1 delineation well and our CO-374 development well.

Highlights

·     The Cascadura-3ST1 delineation well was drilled to a total depth of 8,252 feet, and openhole logs and drilling data indicated a total sand thickness of approximately 900 feet in the targeted Herrera Formation.

·     The Cascadura-3ST1 well has been cased and production testing is scheduled to commence in the third quarter of 2024 directly into the Cascadura natural gas facility.

·     The construction for the flowline from the Cascadura C surface location to the Cascadura natural gas processing facility is progressing, with anticipated completion in the third quarter of 2024.

·     The hazard and operability analysis (“HAZOP”) and engineering designs for the expansion of the Cascadura facility have been approved, and procurement for the expansion has commenced.

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
X
LinkedIn
Touchstone Exploration

More articles like this

Touchstone Exploration

Touchstone Exploration advances growth in Trinidad

Touchstone Exploration solidifies its position in Trinidad’s energy sector with the recent acquisition of the Rio Claro block through its subsidiary, Primera Oil and Gas. Exciting new opportunities await.

Touchstone Exploration

Touchstone expands exploration potential

Touchstone Exploration, through its subsidiary POGL, has secured an exploration and production licence for the Rio Claro block in Trinidad and Tobago. This agreement was finalised in collaboration with the Government of Trinidad and Tobago, the

Touchstone Exploration

Touchstone Exploration reports encouraging well test results at Cascadura

Touchstone Exploration Inc (LON:TXP) has announced the completion of Cascadura-2ST1 and Cascadura-3ST1 well testing. Highlights ·    Cascadura-2ST1 Well: during an extended 48-hour test, Cascadura-2ST1 produced an average rate of approximately 4,950 boe/d, consisting of 26.4 MMcf/d of natural gas