Touchstone Exploration receives CEC to conduct development operations at Cascadura

Touchstone Exploration Inc (LON:TXP) has announced that on August 16, 2022, the Company received a Certificate of Environmental Clearance to conduct development operations within the Cascadura area of the Ortoire block from the Trinidad and Tobago Environmental Management Authority. Touchstone has an 80 percent operating working interest in the Ortoire block, with Heritage Petroleum Company Limited holding the remaining 20 percent working interest.

The CEC approves the construction of a multi-well surface production facility with a designed production capacity of 200 million cubic feet of natural gas per day, 5,000 barrels per day of associated liquids and 200 barrels per day of produced water, with a storage capacity of 8,800 barrels of liquids on the Cascadura A wellsite. In addition to the facility, the CEC includes the drilling of eight wells at two well pads (Cascadura B and C) and the establishment of associated pipelines and infrastructure within the Ortoire block.

Construction of the Cascadura surface facility and associated infrastructure required to bring on production from our two existing Cascadura wells will commence immediately, following the required notifications and conditions set out in the approved CEC. The National Gas Company of Trinidad and Tobago Limited has begun activity in the field to commence the construction of the 1.7 kilometre, 20-inch pipeline to the Cascadura facility.

Paul Baay, Touchstone Exploration President and Chief Executive Officer, commented:

“This is a major step forward for the Cascadura project as we progress from the exploration phase to the development and production phase. It has been a thorough process, but the positive outcome now allows us to establish a clear and measurable five-year development plan for the discovery. We are working with our local contractors, and construction is underway at local fabrication shops for various aspects of the facility with all major facility components already delivered to Trinidad. We will provide updates on the project milestones as we move forward.

Click to view all articles for the EPIC:
Or click to view the full company profile:
Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn

More articles like this

Can Trinidad & Tobago help fill Europe’s gas shortfall?

With Europe pushing hard to reduce their reliance on Russian gas, in the aftermath of the invasion of Ukraine, Trinidad & Tobago’s Liquified Natural Gas (LNG) exports have come into the geopolitical spotlight, and this has also brought

Touchstone’s Trinidad project gets go ahead

Toronto-listed independent Touchstone Exploration on August 17 it had received a certificate of environmental clearance to move ahead with development of its Cascadura gas project in Trinidad and Tobago’s onshore Ortoire block. The sanction from Trinidad’s Environmental Management

Young optimistic over new Touchstone wells

Energy Minister Stuart Young has expressed optimism over two new wells being drilled onshore in the Ortoire Licence area by an independent Canadian company, Touchstone Exploration. These are the Coho and Cascadura wells. In a tweet on Wednesday,

Touchstone Exploration sales lifted by higher oil prices

Touchstone Exploration Inc – Calgary, Canada-based upstream oil and gas company – Achieves quarterly average crude oil production volumes of 1,420 barrels per day, up 2% on a quarter before and up 1% year-on-year. Achieves petroleum sales of

Touchstone Exploration excited to ramp up production (VIDEO)

Touchstone Exploration (LON:TXP) CEO Paul Baay joins DirectorsTalk Interviews to discuss the Environmental Impact Assessment. Now that the Environmental Management Authority have confirmed that the Environmental Impact Assessment is complete Paul explains what this means for the Cascadura well,

Touchstone Exploration CEC application in process

Touchstone Exploration Inc (LON:TXP) has announced that the Trinidad and Tobago Environmental Management Authority has confirmed that no further information is required regarding the Cascadura Environmental Impact Assessment. The Cascadura EIA supports the Company’s application for a Certificate of

Touchstone prepares for Coho launch in Trinidad

Touchstone Exploration has filed a notice to local residents that it will start pre-commissioning and commissioning operations at the Coho gas facility at the Ortoire block in Trinidad and Tobago, the London-listed company announced on August 3. Coho is one

Touchstone Exploration progressing towards full commercial production

Touchstone Exploration Inc (LON:TXP) has announced that the Company has summitted a notice to residents in the community that the Coho gas facility and pipeline will commence pre-commissioning and commissioning operations. Pursuant to the Coho Certification of Environmental

Touchstone to meet with EMA

Touchstone Exploration has provided an additional update on the status of an Environmental Impact Assessment for the Cascadura area of its Ortoire block. In a statement, the company noted that the EIA, which is in support of an

Touchstone projects high gas yield from Cascadura field

By 2023, the Touchstone Exploration (Trinidad) Ltd Cascadura Field project is expected to produce up to 200 million standard cubic feet per day (mmscf/d) of natural gas with the aid of its new separators. On Friday, the company