Valeura Energy increases oil production in Thailand after successful drilling

Valeura Energy, an oil and gas company based in Canada, has successfully boosted production from its Nong Yao field, located offshore Thailand. The company achieved this by completing the drilling operations for the Nong Yao C extension in early August 2024. The extension project involved six planned horizontal development wells, a water injection well, and an additional successful appraisal well. Production from the first wells began on August 15, 2024, and the remaining wells came online shortly thereafter, including a seventh well which was completed as a producer.

As a result of the Nong Yao C development, output from the field has increased by 66%, with recent production rates averaging 11.6 thousand barrels per day during the last week of the third quarter, compared to 7.0 thousand barrels per day the week before starting the new development. Valeura noted that the drilling program exceeded expectations, with total costs coming in about 25% below budget due to faster drilling execution while maintaining high standards for operational safety.

In addition to the progress at Nong Yao, Valeura Energy’s other assets in the Gulf of Thailand have also seen significant activity. At the Wassana field, which the company fully owns, a precautionary suspension of production was implemented before the start of the third quarter to investigate a potential structural risk at the production facility. Following inspection, the facility was confirmed to be in safe operating condition, and production resumed in early August.

At Jasmine field, Valeura successfully drilled two horizontal infill development wells starting in late August. The 41H well encountered 1,982 feet of net oil pay, while the 42H well found 1,555 feet of mixed-phase/oil pay. Both wells were brought into production, delivering an initial rate of 1,050 barrels per day on average. Drilling continued efficiently, with the contracted drilling rig undergoing maintenance before returning to resume infill drilling at Jasmine, where three more wells are planned.

The work program at Manora field has also been adjusted, with more drilling planned than originally anticipated, without any increase in the capital budget. This change is due to the accelerated pace of drilling throughout 2024. The company expects to begin a five-well infill drilling and appraisal programme at its Manora field, where Valeura holds a 70% interest, before the year ends.

The company’s President and CEO, Sean Guest, shared insights into their third-quarter performance, which highlighted both financial strength and organic growth potential. Valeura reported gross revenue of $139 million for the quarter, supported by 1.8 million barrels of oil sold. By the end of the quarter, the company had a cash balance of $156 million, no debt, and 1.2 million barrels in oil inventory. Guest also noted that production from Nong Yao C had driven a 23% increase in oil production during September compared to the second quarter, and that the forecast for production rates for the rest of 2024 remains stable at around 25 thousand barrels per day.

Valeura’s expansion at Nong Yao, along with its other developments in the Gulf of Thailand, illustrates the company’s focus on operational efficiency and organic growth, setting it up for sustained production throughout 2024.

Valeura Energy Inc (TSX:VLE) is an upstream oil & gas company, with a clear strategy to add value for shareholders. The Company has a strong balance sheet positioning it for potential inorganic growth opportunities in the near/medium-term, and substantial longer-term upside potential through an operated deep, tight gas play. 

Click to view all articles for the EPIC:
Or click to view the full company profile:
Facebook
X
LinkedIn
Valeura Energy

More articles like this

Valeura Energy

Valeura Energy completes Jasmine Field drilling, boosting output

Valeura Energy Inc (TSX:VLE, OTCQX:VLERF) has announced the successful completion of an infill drilling campaign at the Jasmine field in Licence B5/27 (100% operated working interest), offshore Gulf of Thailand. Dr. Sean Guest, Valeura Energy President and

Valeura Energy

Valeura Energy completes restructuring of Thai operations

Valeura Energy Inc., a Canadian company focused on petroleum and natural gas exploration and production, recently finalised a reorganisation of its subsidiaries in Thailand. This internal restructuring now consolidates Valeura’s interests in the Nong Yao, Manora,

Valeura Energy

Valeura Energy driving growth and innovation in Thailand

Valeura Energy, a Canadian oil and gas firm, has carved a significant presence in the Gulf of Thailand, strategically positioning itself as one of the leading producers in the region. Since acquiring assets from KrisEnergy and

Valeura Energy

Opportunities for energy development in Thailand

Thailand presents a unique opportunity for energy exploration and production. The country benefits from proven petroleum systems and relatively favourable offshore operating conditions in shallow waters. Mid-life oil fields offer potential to extend their lifespan through

DirectorsTalk

Valeura Energy sees successful oil production growth

Valeura Energy Inc. has reported a significant milestone in the ramp-up of oil production at its Nong Yao C development, located in Licence G11/48, offshore in the Gulf of Thailand. The entire Nong Yao complex is

Valeura Energy

Valeura Energy’s Nong Yao C development project

Valeura Energy Inc (TSX:VLE) is an upstream oil & gas company, with a clear strategy to add value for shareholders. The Company has a strong balance sheet positioning it for potential inorganic growth opportunities in the near/medium-term, and